St. Paul College

Transportation & Applied Technology Lab Renovations
Description:
Phase 1 of this project includes remodeling of a protion of the vocational trades shop areas, classrooms and office space on the ground floor and new construction for a connecting link between the east and west tower buildings. The remodeling prioritizes life safety, air quality and deferred maintenance improvements. Exiting improvements include a new exit corridor and a new exit hall connection on the ground floor. The renovation includes space-use modifications, better lighting and improved ventilation with new air handling equipment and exhaust systems for trades shop and classrooms.
The new connecting link will greatly improve circulation and traffic flow between the two existing building towers on the second, third and fourth floors. These towers are currently connected only on the first floor. The link will also provide office, meeting and student interaction spaces.
Phase 2 of this project includes the remodeling of the remaining vocational trades shop areas on the ground floor for space-use modifications, life safety, air quality and deferred maintenance improvements. Some new construction is projected to address current space deficit conditions, including a small expansion of the truck mechanics shop, a new east entry vestibule and new mechanical equipment penthouses to serve the shop areas.
2004 Capital Budget Request (Funded in 2005, adjusted for inflation, see below)
| Project Funding: | |
| $10,993,000 $3,000,000 $13,500,000 $27,493,000 |
2005 State G.O. Bonds 2006 State G.O. Bonds 2008 State G.O. Bonds |
Location: St. Paul, MN
Gross Square Feet:
Phase 1: Renovation - ±92,500 GSF; New - ±7,500 GSF
Phase 2: Renovation - ±106,000 GSF; New - ±5,200 GSF
Building Footprint: Renovation of existing space
Number of Stories: One (Ground Floor); Three (connecting link between towers)
Exterior Finishes: Brick, glass, curtain wall, metal panels (connecting link)
Project Substantial Completion: Phase 1 - June 2008; Phase 2 - August 2009
Current Project Status: Phase 1 - Complete; Phase 2 - Construction
Contact Information:
- Campus Project Representative: Tom Doody
- Architect/Engineer: TKDA
- General Contractor: Phase 1 & Phase 2: L.S. Black Constructors
- Owner's Representative: Hansen Construction Consulting
- Program Manager: Barry Schaub
- Campus website: St. Paul College
Project Schedule: