Southwest Minnesota Sate University

Science Labs Renovation
Description:
This project is to renovate agronomy, environmental science, physical science, astronomy, physics and plant science labs in the Science and Math building and an addition to the Plant Science Lab. These renovations will provide updated academic spaces for the science and laboratory curricula.
2008 Capital Budget Request (Partially funded for design in 2008 see below)
Location: Marshall, MN
| Project Funding: | |
| $200,000 $5,644,000 $5,844,000 |
2008 State G.O. Bonds (Design) 2010 State G.O. Bonds (Construction) (Planned) |
Gross Square Feet: New: ±3,200 GSF; Renovated: ±20,000 GSF
Building Footprint:
Exterior finishes: Existing
Project Substantial Completion: May 2012
Current Project Status: AE selection
Contact Information:
- Campus Project Representative: Cyndi Holm
- Architect/Engineer: TBD
- General Contractor: TBD
- Owner's Representative: TBD
- Program Manager: Barry Schaub
- Campus website:Southwest Minnesota State University
Schedule: